Contents



Housing and Construction Standards

Letters of Assurance

Letters of Assurance

Proposed Code Changes

1.4.1.2 Defined Terms
Add:

Registered professional of record means a registered professional retained to undertake design work and field review pursuant to Clause 2.2.7.2.(1)(b) in Division C.


2.2.7.1. Application
Modify:

1) The requirements of this Subsection apply to an owner who applies for a building permit for all components of a building that fall within the scope of Part 3 in Division B.

2) The requirements of the Subsection apply to the following components of a building that fall within the scope of Part 9 in Division B:

  • a) structural components of buildings that fall within the scope of Part 4 in Division B (See Appendix A.),

  • b) geotechnical components that are beyond the scope of Part 9 in Division B (see Appendix A),

  • c) sprinkler systems designed to NFPA 13 and standpipe and hose systems designed to NFPA 14, or

  • d) buildings that are designed with common egress systems for the occupants and require the use of firewalls according to Article 1.3.3.4. of Division A.


2.2.7.2. Owner Responsibilities

1) Before an owner obtains a building permit from an authority having jurisdiction, constructs or alters a building, the owner shall

  • a) retain a coordinating registered professional to coordinate all design work and field reviews of the registered professionals required for the project in order to ascertain that (See Appendix A.)

    • i) the design will substantially comply with the British Columbia Building Code and other applicable enactments respecting safety, and

    • ii) the construction of the project will substantially comply with the British Columbia Building Code and other applicable enactments respecting safety, not including the construction safety aspects, and

  • b) when a building permit is required, deliver to the authority having jurisdiction letters, in the forms set out in Schedules A, B-1 and B-2 and B (See the end of Division C.) (See Appendix A.)

2) Where an occupancy permit or final inspection from an authority having jurisdiction is required and before an owner obtains an occupancy permit or final inspection from an authority having jurisdiction, occupies, or receives permission to occupy the building, the owner or coordinating registered professional shall deliver to that authority having jurisdiction letters in the forms set out in Schedules C-A and C-B. (See Appendix A.)

2.2.7.3. Registered Professional Responsibilities

1) A registered professional of record who signs a letter, the form of which is set out in a schedule to this Section, and an owner who signs or has an agent sign a letter the form of which is a set out in a schedule to this Section, shall comply with this Section and the provisions of the letter that apply to the person signing.

2) A registered professional of record or coordinating registered professional who is responsible for a field review shall keep a record of the field review and of any corrective action taken as a result of the field review and shall make the record available to the authority having jurisdiction on the request of that authority.

3) A registered professional of record who is retained to undertake design work and field reviews and who is required to provide letters pursuant to Clause 2.2.7.2.(1)(b) shall

  • a) place his or her professional seal or stamp on the plans and supporting documents submitted by him or her in support of the application for the building permit, after ascertaining that they substantially comply with the British Columbia Building Code and other applicable enactments respecting safety,

  • b) provide to the authority having jurisdiction coordinating registered professional the Schedule C-B (See the end of Division C) after ascertaining that the components of the project for which the registered professional of record is responsible are constructed so as to substantially comply, in all material respects, with

    • i) the plans and supporting documents, and
    • ii) the requirements of the British Columbia Building Code and other applicable enactments respecting safety, not including construction safety aspects.
  • c) ensure that the field reviews that are necessary to comply with Clause (b) are properly completed.


2.2.7.4. Termination

1) The owner and the coordinating registered professional shall each notify the authority having jurisdiction of the date the coordinating registered professional ceases to be retained at any time during the project's construction.

2) The coordinating registered professional shall notify the authority having jurisdiction of the date a registered professional of record ceases to be retained at any time during the project's construction.

3) The registered professional of record shall notify the coordinating registered professional and the authority having jurisdiction of the date the registered professional of record ceases to be retained at any time during the project's construction.

4) Notification under Sentences (1), (2) and (3) must be made before the coordinating registered professional or the registered professional of record ceases to be retained or, if that is not possible, then as soon as possible.

5) The owner must not terminate the appointment of a coordinating registered professional or a registered professional of record unless

  • a) the owner immediately replaces the coordinating registered professional or the registered professional of record, or

  • b) the owner has complied with Section Clause 2.2.7.2.(1)(b) and Sentence 2.2.7.2.(2) by delivering letters in the forms set out in Schedule A, B-1, B-2, C-A and C-B to the authority having jurisdiction.

Division C – Appendix A

A-2.2.1.2.(1) Structural Design. Part 4 of Division B is written on the assumption that structural design will be carried out by a professional who is qualified to perform such design. Sentence 2.2.1.2.(1) is not intended to imply that a professional may not also be required in the application of requirements in other Parts of the NBC BCBC.

A-2.2.7. Professional Design and Review. This Section provides for the use of what are generally called Letters of Assurance. The letters themselves, known as Schedules A, B-1, B-2, C-A and C-B and located at the end of Division C, are intended to put on paper the responsibilities of the owner and various registered professionals of record in a construction project. The Letters of Assurance do not impose any additional responsibilities on the registered professionals nor are they intended to alter the roles and responsibilities of the authorities having jurisdiction.

The Schedules have been very carefully scrutinized by the Province of British Columbia, Union of BC Municipalities, Building Officials’ Association of BC, Architectural Institute of BC, Association of Professional Engineers and Geoscientists of B.C. and their respective legal counsel. The precise wording in the letters is extremely critical and must not be modified. For this reason, authorities having jurisdiction will only accept copies of the original master Schedules as published in Division C. Any notations on these Schedules which are absolutely necessary to suit a particular project must be clearly and legibly marked in pen on the copies.

It is typical that the registered professional responsible for the design is also responsible for the field review. However, tThere are instances where this is not the case and having a different registered professional doing the field reviews is unavoidable a different registered professional is hired for the field reviews. Schedule C-B requires that the registered professional that provides the field review provide assurance that provides assurance that the building as finally constructed is in substantial conformance with the Code. It may be unreasonable to expect a separate field reviewer to take on the responsibility for Code compliance of a design done by others. . It is unreasonable to expect the field reviewer to take on the responsibility for Code compliance of the design done by others. In the event of transition, Schedule C-B must be clarified by the field reviewer by crossing out and initialing Clause (b)(i) and providing the effective transition date. Under such circumstances it is acceptable for the registered professional responsible for the design to cross out and initial the paragraph related to field reviews on Schedule B and for the registered professional responsible for the field reviews to cross out and initial the paragraph related to design and Code conformance.

Note that Schedules A, B-1, B-2, C-A & C-B, as required by Subsection 2.2.7., must be signed and sealed and submitted to the authority having jurisdiction, as applicable for each specific project. Conditional or qualified Schedules are not typically acceptable. Any fire and life safety deficiency that would prevent the issuance of a Schedule must be remedied before the Schedule is released, not accommodated by conditions or qualifications placed on the Schedule. See the Guide to Letters of Assurance, available from the Building and Safety Policy Branch Web site, for more details.

There are a few locations in the Province where building permits are not issued and there is no authority having jurisdiction. In such circumstances, it is recommended that the coordinating registered professional retain the Letters of Assurance with the project documents. The schedules are a valuable record of the registered professionals who assured the building’s substantial code conformance.

A-2.2.7.1.(1)(b) Structural Components. The reference to “structural components of buildings that fall within the scope of Part 4” includes the situation where a building is classified under Part 9 due to its size and occupancy but also contains some structural components (such as beams supporting concentrated loads) which must be designed under Part 4. In this situation only Schedules B-1, B-2 and C-B for the structural components are required. Schedule A and Schedules B-1, B-2, C-A and C-B relating to non-structural components are not required. Refer to Appendix A-9.4.1.1. and A-9.4.1.1.(3) in Division B for structural design of Part 9 buildings for lateral wind and earthquake loads.

A-2.2.7.2.(1)(a) Coordinating Registered Professional. The coordinating registered professional is responsible to ascertain that all Code related aspects which are relevant to the project are clearly identified by each of the registered professionals of record in the collection of Schedules B-1 and B-2. If a registered professional of record has crossed out any item on their Schedule B-2, the coordinating registered professional must confirm this item is not applicable to the project or resolve the issue with the registered professional of record. Only under very unusual circumstances should additional registered professionals within a single discipline be expected to submit Schedules B-1, B-2 and C-B to the coordinating registered professional.

A-2.2.7.2.(1)(b) Schedule B-2. The purpose of Schedule B-2 is to clearly identify the appropriate registered professional of record who has the overall responsibility in each discipline for compliance with the various code-related aspects of the project. Detailed design of certain building components may be undertaken by a second registered professional. It is common in the industry for detailed sprinkler design or detailed structural design of open web steel joists to be performed by a second registered professional who may be retained by the contractor or the fabricator. The registered professional of record fulfills their obligation for overall responsibility of Code compliance as indicated in Schedule B-2 by reviewing the shop drawings which are prepared under the direction of the second supplemental registered professional. Such shop drawings must bear the professional seal and signature of the second supplemental registered professional. Field review of these components can be undertaken by either the registered professional of record or the supplemental second registered professional. In the event that the supplemental second registered professional provides the field review, the registered professional of record must be satisfied that such field reviews have been performed and is ultimately responsible for Schedule C-B.

A-2.2.7.3. Demonstration of the Coordinated Fire & Life Safety Systems. The design drawings and supporting documents must clearly indicate all essential details of the coordinated fire and life safety systems prior to issuance of a building permit. Demonstration of the proper, integrated operation of the fire and life safety systems must be conducted prior to occupancy. The following is an example of the steps required to co-ordinate the installation and testing of fire and life safety systems in buildings.

1.0. General

Referencing Schedule B-2:

  • Item No. 1.12 “Functional Testing of Architecturally Related Fire Emergency Systems and Devices,”
  • Item No. 3.4 “Functional Testing of Mechanically Related Fire Emergency Systems and Devices,”
  • Item No. 4.5 “Functional Testing of Plumbing Related Fire Emergency Systems and Devices,”
  • Item No. 5.13 “Functional Testing of Fire Suppression Systems and Devices,” and
  • Item No. 6.3 “Functional Testing of Electrical Related Fire Emergency Systems and Devices.”

The coordinating registered professional (CRP) and registered professionals of record (RPRs) must demonstrate that the fire and life safety systems' design has been coordinated prior to the issuance of the building permit. That is, the CRP/RPRs must accumulate and submit the necessary documentation, such as:

  • complete drawings,
  • schedules,
  • schematic diagrams,
  • fire alarm system sequencing description(showing coordination between mechanical and electrical fire protection and life safety systems),
  • mechanical fire protection and life safety schematic riser diagrams,
  • electrical fire alarm riser diagram,
  • motor data list coordinated with fire alarm system sequencing,
  • other documentation, as appropriate,

to demonstrate that the interface of the fire and life safety systems has been designed and coordinated so that when built correctly they will function as an integrated system. Further, it is intended that when the construction of the fire and life safety systems is indicated by the contractor to be complete, the RPRs/CRP witness the demonstration of the testing of the fire and life safety systems to confirm compliance that the as-built systems function as intended by the design.

The required list of items will depend on the simplicity or complexity of the project. The following is a comprehensive list of items for fire and life safety systems for a complex project which need to be coordinated in order to demonstrate compliance:

Notes: It is the responsibility of the coordinating registered professional (CRP) and registered professionals of record (RPRs) to determine the best method of “how to” demonstrate to the authority having jurisdiction (AHJ) that the fire protection and life safety systems have been coordinated for each project. That is, the method(s) used (i.e., charts, drawings, matrices, tables, etc.) for demonstration purposes should be project-specific and relate only to that project.

It is not the intent of this Appendix material to dictate or produce “checklists” or other prescriptive methods for demonstrating compliance since this is best left to the professional discretion of the appropriate CRP/RPRs.


3.0. Roles and Responsibilities for the Demonstration of the Coordinated Fire and Life Safety Systems

3.1. Roles and Responsibilities for the Design, Commissioning and Functional Testing of Fire and Life Safety Systems

3.1.1. Design Phase

RPRs will clearly indicate on their drawings and supporting documents the details of the fire and life safety systems for each applicable item of Section 2 for their particular discipline. RPRs will also coordinate the design of the components in their system with the designs of other RPRs on the project. RPRs and supplemental RPs are to indicate what functional testing, system verification, etc., must be performed by the contractor or sub-trades and establish the documentation to be provided.

The CRP will act as the facilitator for the coordination of the design of the fire and life safety systems among the various RPRs.

3.1.2. Construction Phase

The contractor will coordinate the activities of the sub-trade contractors for the installation of the fire and life safety systems in accordance with the contract documents.

RPRs will provide field reviews to ascertain that the construction of the fire and life safety systems substantially complies with their design.

RPRs will review shop drawings of the fire and life safety systems to determine that they accurately reflect their design intent. They will also coordinate their reviews with those of the other RPs on the project.

The CRP will coordinate the shop drawing reviews and field reviews by the RPRs with the objective that the entire fire and life safety system will correctly operate as an integrated system.

3.1.3. Occupancy Phase

The contractor will coordinate the sub-trade contractors for the commissioning and functional testing of the fire and life safety systems. The contractor will also collect all of the required occupancy submission documents from the various sub-trade contractors and forward them to the CRP.

The CRP will take the lead role in coordinating the activities of the RPRs required for the commissioning and functional testing of the fire and life safety systems. The CRP will develop the project-specific test protocol and procedures in consultation with the RPRs and distribute them to the various parties involved in the process.

RPRs will ascertain that the appropriate commissioning and functional testing of the fire and life safety systems of the components in their disciplines have been satisfactorily completed by the sub-trade contractors. They will also determine that the appropriate occupancy submission documents have been submitted and filled in correctly.

The CRP will be responsible for collecting all of the required occupancy submission documents, reviewing them for completeness and accuracy, and forwarding them to the AHJ in a complete package prior to the coordinated final AHJ review.

3.2. Sample Summary of Roles and Responsibilities for Demonstration of the Coordinated Fire and Life Safety Systems

The following is a sample summary (only) of the roles and responsibilities for a typical high-rise building with underground parking. The precise roles and responsibilities for each project will vary depending on the complexity. The CRP will ascertain that the appropriate roles and responsibilities for each project are fulfilled by the RPRs.

3.2.1. Coordinating Registered Professional

Design Phase

  • Determine the appropriate RPRs required for the project and make arrangements with the owner for their services. It is the responsibility of the RPRs to determine the need for supplemental RPs.
  • Clarify the roles and responsibilities of the various RPRs.
  • Coordinate the design of the fire and life safety systems by the RPRs.
  • Coordinate and develop the test protocol and procedures for functional testing of the fire and life safety systems.
  • Coordinate any alternative solutions included in the design.
  • Coordinate the submission of the design drawings and supporting documents for the building permit application.

Construction Phase

  • Coordinate and monitor the field reviews of the RPRs.
  • Coordinate and monitor the review of shop drawings by the RPRs.
  • Coordinate the information and its circulation among the RPRs and contractor.

Occupancy Phase

  • In conjunction with the RPRs, compile the project-specific test protocol and procedures for the fire and life safety systems, and review the requirements with the contractor, sub-trades and RPRs.
  • Compile the list of project-specific occupancy permit submission documents and the schedule for submissions and confirm completeness with AHJ.
  • Organize the "Coordinated Final Consultant Review" at least one week prior to "Coordinated AHJ Final Review."
  • Coordinate the functional testing of the fire and life safety systems during the "Coordinated Final Consultant Review."
  • Coordinate the RPRs' review of occupancy submission documents for completeness and accuracy.
  • Coordinate certification of equivalencies alternative solutions, if applicable.
  • Collect all of the required occupancy submission documents and submit them in a complete package to the AHJ.
  • Organize the "Coordinated AHJ Final Review."
  • Record any deficiencies identified at the "Coordinated AHJ Final Review" and monitor RPRs' field review of the corrective actions by the contractor.
  • Assist in finalizing the list of outstanding requirements which need to be met prior to occupancy.

3.2.2. Architectural

Design Phase

  • Determine which supplemental RPs, if any, may be involved in the project.
  • Establish the conceptual design for the fire and life safety systems in consultation with any supplemental RPs.
  • Determine equivalency alternative solutions reports required and coordinate the implementation on the drawings and supporting documents.
  • Clearly indicate on drawings and supporting documents:
    • major occupancies and code classifications.
    • fire separations and fire-resistance ratings.
  • Closures:
    • Fire-protection rating
    • Temperature rise requirements
    • Amount of glazing
    • hardware
    • Quick release hardware
    • Hold-open devices
    • Electromagnetic locks
  • Egress systems.
    • provisions for fire fighting access.
    • interior and exterior finishes.
    • elevating devices c/w integrated controls to the fire alarm panel.
    • signage coordinated with fire alarm system and annunciation.

Construction Phase

  • Provide field reviews of architectural components.
  • Review shop drawings for architectural components and coordinate requirements with other RPs.
  • Review shop drawings for other disciplines which may influence architectural components.

Occupancy Phase

  • Ascertain that the architectural components substantially conform to the architectural drawings and supporting documents.
  • Witnessing the functional testing of the architectural components of the fire and life safety systems.
  • Coordinate the signage with the fire alarm annunciator and the fire safety plans.
  • Review the architecturally-related occupancy submission documents provided by the contractor, and sub-trades, and any supplemental RPs, for completeness and accuracy.
  • Prepare and forward to the CRP the architectural Schedule C-B and other applicable supporting documents required prior to occupancy.

3.2.3. Mechanical/Plumbing

Design Phase

  • Determine which supplemental RPs, if any, may be involved in the project.
  • Coordinate mechanical/plumbing clearances and functional requirements with other RPRs.
  • Clearly indicate on drawings and supporting documents:
    • details of the mechanical/plumbing components of the fire and life safety systems.
    • schematic diagram of the smoke venting system showing all fans, ducts, motorized dampers, fusible link dampers and backdraft dampers.
    • location and fire-protection ratings of fusible link fire dampers and fire stop flaps.
    • location and fire-protection ratings of motorized fire dampers.
    • location and fire-resistance ratings of fire-rated duct enclosures.
    • fire stop systems for mechanical/plumbing penetrations of fire separations.
    • kitchen exhaust system/suppression system.
  • Mechanical fans/motorized dampers sequence of operations:
    • Describe operation under normal mode.
    • Describe operation under fire alarm mode.
    • Indicate fire alarm initiation devices that activate change of operation.

Construction Phase

  • Provide field reviews of mechanical/plumbing components.
  • Review shop drawings for mechanical/plumbing components and coordinate requirements with other RPRs.
  • Review shop drawings for other disciplines which may influence mechanical/plumbing components.

Occupancy Phase

  • Ascertain that the mechanical/plumbing components substantially conform to the mechanical/plumbing drawings and supporting documents.
  • Witnessing the functional testing of the mechanical/plumbing components of the fire and life safety systems.
  • Review the mechanical/plumbing related occupancy submission documents provided by the contractor, and sub-trades and any supplemental RPs for completeness and accuracy.
  • Prepare and forward to the CRP the mechanical/plumbing Schedule C-B and other applicable supporting documentation required prior to occupancy.

3.2.4. Fire Suppression

The assurance of sprinkler systems can be accomplished under two possible scenarios:

Scenario 1

  • The engineer of record RPR undertakes the complete detailed sprinkler system design prior to the building permit application.
  • The engineer of record RPR submits Schedules B-1 and B-2 with the BP application.
  • The engineer of record RPR provides field reviews during construction and submits a Schedule C-B prior to occupancy.

Scenario 2

  • The engineer of record RPR provides a detailed performance specification for the sprinkler system design, as well as sufficient documentation to demonstrate/assure layout feasibility and interface with other components.
  • The engineer of record RPR submits Schedules B-1 and B-2 with the BP application for overall coordination of the sprinkler design.
  • The performance specifications may include a requirement that a separate supplemental RP for sprinkler design engineer be responsible for detailed sprinkler design, preparation of sprinkler shop drawings (signed and sealed) and hydraulic calculations, letters of assurance Schedules B-1 and B-2, field reviews during construction, and Schedule C-B (for detailed design) prior to occupancy.
  • The engineer of record RPR reviews the detailed sprinkler design and shop drawings to ascertain that they substantially comply with the performance specifications.
  • The engineer of record RPR provides a Schedule C-B prior to occupancy to confirm overall coordination of the sprinkler design and installation. The engineer of record RPR is entitled to rely upon the professional seal of the supplemental RP for sprinkler design engineer for the detailed design and field review of the sprinkler system.

3.2.5. Electrical

Design Phase

  • Liaise with the CRP and RPRs to ensure that the test protocol and procedures for functional testing of the fire and life safety systems are consistent with the electrical design.
  • Details of the electrical components of the fire and life safety systems.
  • Clearly indicate on drawings and supporting documents:
    • Fire Alarm System
      • Location of fire alarm annunciator panel and central alarm control facility
      • Location of fire alarm initiating devices, e.g., smoke detectors, heat detectors, manual pull stations.
      • Fire alarm riser diagram c/w ancillary device connections
      • Audibility of fire alarm signal throughout floor area
      • Zoning of fire alarm initiation devices and audible signal appliances
      • Monitoring of fire alarm
      • Routing and method of protection of emergency conductors
      • Wiring methods for equipment
      • Testing/verification and documentation requirements and the documentation to be submitted to the RPR
    • Sprinkler System
      • Coordinate design with fire suppression registered professional.
      • Sprinkler system alarm initiation and monitoring to be indicated on the fire alarm riser diagram, e.g., flow, tamper, pressure.
      • Detailed diagrams for freeze protection systems, e.g., heat trace monitoring, low temperature monitoring.
    • Fire Pump Systems
      • Riser diagram to indicate monitoring of the fire pump, e.g., pump running, power failure, phase reversal, wiring details for device connections.
      • Routing and method for protection of fire pump feeders from fire and power source, so that a fire from one source will not interrupt power from the other source
      • Electrical requirements to appropriate Standard and documents to be submitted to RPR, e.g., overcurrent protection details, location of controller and transfer switches, voltage drop.
    • Kitchen Exhaust/Fire Suppression System
    • Emergency Generator
      • Generator load calculations
      • Details and wiring diagram for monitoring through the fire alarm system
      • Details for testing to appropriate Standard and documents to be submitted to RPR
    • Smoke Venting Systems
      • Coordinate design with the mechanical engineer
      • Fire alarm riser diagram to indicate smoke venting fans and motorized dampers and HVAC/exhaust fan shutdown
      • Detailed wiring diagrams for fan shut-offs, exhaust fan operation, pressurization fan operation, damper operation (opening, closing, throttling)
      • Sequence of operation of smoke venting system in a narrative form
      • Describe operation under normal mode
      • Describe operation under fire alarm mode
      • Indicate fire alarm initiating devices that activate changes of operation/sequence
      • Routing methods for protection of emergency conductors
    • Electromagnetic Locks and Hold-Open Devices (Security)
      • Coordinate design with the architect
      • Sequence of operation in both normal and fire alarm mode
      • Wiring diagrams for connection of devices
      • Locations of devices on the floor plans
    • Elevators
      • Sequence of operation in a narrative form
      • Wiring diagram details
      • Routing and method of protection of emergency conductors
    • Fire stop systems for electrical penetrations of fire separations
    • Coordinate electrical equipment location and functional requirements with other RPRs/CRP.

Construction Phase

  • Provide field reviews of electrical components.
  • Review shop drawings for electrical components and coordinate requirements with other RPRs.
  • Review shop drawings for other disciplines which may influence electrical components.

Occupancy Phase

  • Ascertain that the electrical components substantially conform to the electrical drawings and supporting documents.
  • Witnessing the functional testing of the electrical components of the fire and life safety systems.
  • Review the electrical-related occupancy permit submission documents provided by the contractor, and sub-trades and any supplemental RPs for completeness and accuracy.
  • Prepare and forward to the CRP the electrical Schedule C-B and other applicable supporting documents required prior to occupancy.

4.0. Sample Occupancy Demonstration/Witnessing Flowchart

DEVELOP TESTING PROTOCOL/PROCEDURE (Design Phase)
CRP/RPRs develop Testing Demonstration/Witness Protocol
— Issue to Authorities Having Jurisdiction & Contractor
DOCUMENTATION SUBMISSION
Contractor/Sub-trades submit/deliver all appropriate
documentation to CRP/RPRs, including:
  • — The original Contractor's Materials and Test Certificate for the sprinkler system
  • — The original Contractor's Materials and Test Certificate for the sprinkler system
  • — Fire Pump Flow Test Certificate(s)
  • — Back Flow Prevention Certificate(s)
  • — Emergency generator commissioning and verification reports
  • — The original Certificate of Verification for the fire alarm system
  • — Appendix "A" to the fire alarm verification report
  • — ULC Certificate for Protective Signaling Service
  • — Other documentation, as appropriate
CONTRACTOR DEMONSTRATION — CONSTRUCTION COMPLETE
Contractor & Sub-trades
(Mechanical, Electrical, Elevator, Sprinkler, Fire Alarm, etc.)
as appropriate
COORDINATED FINAL CONSULTANT REVIEW DEMONSTRATION/WITNESSING
CRP/RPRs
(Architect, Mechanical Engineer, Electrical Engineer, Sprinkler Engineer, Equivalency Consultant, etc.) as appropriate
OCCUPANCY SUBMISSION DOCUMENTS
CRP to collect all submission documents, including Schedule Cs from RPRs,
and submit to AHJ in a complete package

COORDINATED FINAL AHJ REVIEW DEMONSTRATION/WITNESS
Contractor, Sub-trades, CRP/RPRs demonstrate to AHJ (Building, Fire, Mechanical, Electrical and Sprinkler)



OCCUPANCY